This project is complete,
5.04.18 - Waiting on fire marshall approval and final clean.
4.02.18 - Waiting on fire marshal approval.
3.23.18 - Landscaping is underway. The building is complete. Addressing punch out items, cleaning up site, and waiting for power,
1.25.18 - Pouring retaining walls,
1.08.18 - Crewmen are currently taping and floating,
12.13.17 - Crews poured paving this morning,
10.30.17 - Building is sheeted and interior framing underway,
10.25.17 - Sheeting continues,
10.15.17 - Crewmen are hanging steel,
10.06.17 - Pouring the foundation,
9.15.17 - Pad progress,
7.31.17 - Working on the pond and site grading,
6.28.17 - Site work began mid-June.
5.31.17 - Sitework will soon begin for the first of 10 buildings in a new business park off Clay Road in Katy. This first building will be 12,374 SF (Total) with a 2,708 SF office and 9,666 SF Warehouse.
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/