Independence Business Park Phase 3
6.24.24 - Final interior photos,
6.11.24 -
5.29.24 - Landscaping is installed for both buildings,
5.17.24 - Lights are on,
3.05.24 - Landscaping is soon to follow,
2.24.24 - Sidewalks are poured,
2.22.24 - Paving is poured and cured. Curbs have been poured. Masonry work is complete.
2.06.24 - Sitework is underway preparing for the next paving pour. Interior buildout continues,
1.11.24 - Masonry work continues. The metal sheeting and trim is complete and windows are installed. Interior buildout continues,
12.11.23 - The building is fully sheeted and the interior buildout is underway. The parking has been poured and is curing,
11.02.23 - All iron is in place and sheeting is underway,
10.02.23 - M&M Erectors are haning the main frame collumns,
9.01.23 - Sitework continues,
7.17.23 - Site crews began to scrape the site for the third phase of the Independence Business Park for Finial Group. We are building three office / warehouse buildings total (Building 2, Building 6, and Building 7, each being pre-engineered metal buildings with horizontal architectural panels and limestone offices. Bldg 2 will be 46,378 SF with a 2,855 SF office. Building 6 will be a 18,525 SF crane-ready building with a 2,025 SF office, and Building 7 will be a 25,425 SF crane-ready building with a 2,025 SF office.