This project includes a 7,150 SF single slope warehouse, with three overhead bay doors, liner panel, a fully insulated roof and fully insulated walls.
9.16.24 - The foundation was poured this morning and is curing,
9.13.24 - Crews are forming the pad for the foundation pour,
9.10.24 - Crewmen are pouring piers,
8.26.24 - Crewmen are pouring the truck well walls,
8.14.24 - Crewmen are pouring the loading dock,