10.11.24 - Crews have progressed to sheeting the building,
10.03.24 - Erectors are hanging steel as pond work continues,
9.23.24 - The foundation has cured,
9.14.23 - Crews are pouring the building foundation,
9.10.23 - Crews are forming for the foundation pour,
8.14.24 - Storm and sewer work continue. Crews are working on the pond and forming the pad,
8.05.24 - Sitework continues. Prepping for the future pad.
6.28.24 - The walls have cured,
6.20.24 - Crews continue to work on the fencing and the pond,
6.10.24 -
6.08.24 - Working on the fence,
6.06.24 - Building forms,
This project consists of a 32,000 SF office/warehouse combination with a 2nd floor mezzanine and office area. Phase II construction will consist of a 42,000 SF lumber canopy.
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/