Secor

Secor | Rock Yard | Cypress, TX

7.06.20 - We submitted the As-built certificates and are waiting for the final inspection. Centerpoint was onsite last week to set markers for the electrical service poles, for the lift station.

6.17.20 - Engs As-built inspection took place today. Once we receive the Engs As-built certificate, we can submit to Harris Co flood control and request final inspections for power release,

5.28.20 - Crewmen are pumping water to finish the storm water lift station.

5.11.20 - Rock yard is complete. Retention ponds are dry and final graded. Installing the last of the storm pipe lift station.

4.15.20 - Laying flex base for rock yard. Completing final dress up of retention ponds.

3.09.20 - Crewmen are cutting grades on the detention pond and storm swale,

3.02.20 - The pond is dried and crews are cutting grades,

2.21.20 - Crewmen continue to work on the pond. Grades have been cut and the storm as been installed. 

12.30.19 - Dennis Montesinos will soon oversee this project in Cypress, which calls for a two-acre rock yard. 