10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,
9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,
9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,
8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,
6.03.19 - Electricians are running extra grounding and cad welding to the columns,
4.29.19 - Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,
4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,
4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,
3.29.19 - Liner panels are being installed,
3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,
3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,
2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,
1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,
1.07.19 - Hanging rafters,
12.18.18 - Crews began hanging steel last week,
12.03.18 - The foundation has been saw cut,
11.29.18 - The foundation was poured this week,
11.19.18 - Crewmen are tying double rebar mat for the foundation,
10.21.18 - Crewmen have drilled 27 of the 32 piers,
9.24.18 - Crews are building pad for the foundation,
9.07.18 - Site excavation continues,
8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/