Big City Manufacturing | 23,000 SF | Friendswood, TX
1.23.24 - Final clean is complete. Landscaping is installed.
12.14.23 - Parking area striping is complete,
11.29.23 - Glass installation is complete and the ceilings are installed. Power should be turned on next with an expected completion set for next month,
10.25.23 - Interior crews are hanging sheetrock. Concrete crewmen are getting ready to pour the equipment pad,
7.25.23 - Crews poured the foundation this morning.
7.20.23 - Crewmen are preparing for next week's pour,
5.25.23 - Crews are breaking ground on Big City Manufacturing's new facility in Industry Park. This Design/Build project includes a fully air conditioned shop and 3,000 SF of finished office space,