Closner Equipment

Closner Equipment | 20,993 SF Office, Repair Shop, and Washbay | Elgin, TX

6.02.25 - Tile installation is complete. Crews are finishing up with the washbays and with the liner panel installation. Interior flooring is near completion,

ClosnerElgin5.28 3

ClosnerElgin5.28 4

ClosnerElgin5.28

ClosnerElgin5.30

ClosnerElgin6.02

ClosnerElgin6.02 2

 

5.20.25 - Painting and tile installation are underway. Millwork and fence installation continue, as well as the washbay electrical and final rock work,

1AE132A4 7A2E 4A78 A8F4 E77F817063FE copy

02B3EC67 0FA0 47CA BAA0 CAD428992EAB copy

6B86E97F 8639 43D3 8A84 C4C0BB28550F copy

7A682D63 5252 4CEE 99DE 023AE1CF9D12 copy

7B12CD38 2F6B 4E89 BCE1 A7651BB8566C copy

7FD32314 4D10 472D 81A4 60DECCC10C76 copy

3602318B C25A 4630 990E C3BC39DCB1B8 copy

A711083B ABE2 497F 8BF0 26F038A56F48 copy

8DBE57DF 77EA 4734 8FCC FD4ED4ED0E73 copy

4.28.25 - Rough electrical and plumbing continue. Door frames are installed,

43BAF121 7E45 4BD9 A50D 1886EA86C947 copy

017D6195 0EF4 4925 B1FE F332101D9FFF copy

1C669A2F 3EC4 4036 86F1 E306FA297BDA copy

52980850 D2D6 4CF2 A0CD F283110DCAC8 copy

A342DFA4 6C3F 4F8D BA47 8F75B73E6CF8 copy

 

3.26.25 - Interior buildout is underway,

closner elgin3.26

closner elgin3.26 8

closner elgin3.26 7

closner elgin3.26 2

closner elgin3.26 3

closner elgin3.26 4

closner elgin3.26 5

closner elgin3.26 6

 

 

2.18.25 - Cremwen are installing metal sheeting and have installed a canopy,

closner elgin feb18

closner elgin feb18 2

closner elgin feb18 3

 

2.16.25 - Crews continue to hang steel for this project,

Closner Feb

Closner Feb2

Closner Feb3

Closner Feb4

 

1.13.25 - Grading of the storage yard is complete. Crews will start hauling in the crushed rock next week.

ClosnerElgin1.13

 

 

12.12.24 - The foundation is poured and is curing,

12.12.24

 

12.09.24 - Crews are forming for the foundation pour,

12.09.24

12.05.24 - Crews are pouring piers,

12.05.24

 

10.23.24 - Site crewmen are bringing in fill for the pad,

IMG 2024 10 23 08 26 05 969 copy

IMG 2024 10 23 15 01 00 990 copy

 

10.22.23 - Crewmen continue excavation for the pad,

IMG 2024 10 22 16 13 14 420 copy

 

10.17.24 - Dirt crew started mass grading and excavation for the pad. They will start building the pads for the foundation next week,

IMG 8225 copy

IMG 8226 copy

IMG 8227 copy

IMG 8228 copy

IMG 8229 copy

 

9.23.24 - We participated in a ground breaking ceremnony for Closner Equipment. Closner Equipment is a repeat client of Northwinds. We completed their Waller facility in 2023. Closner is a heavy equipment dealer/repair facility that specializes in road work. Closer has selected Northwinds to design and construction their new facility in Elgin, TX. The facility will be built on a six acre tract located on the US 290 frontage. The improvements include 20,993 SF of buildings to include an office, repair shop, and wash bay. The site work will include asphalt, concrete, and a large rock yard.

20240923 104748

20240923 104827

20240923 104851

20240923 104941

20240923 105007

20240923 105054

 

 

Clover Tool Co.

Related Posts

By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/