Construction is complete on these Industrial Suites.
7.17.23 - The stucco and stone is complete. Crewmen are installing glass.
4.14.23 -The masons started their work on the stucco. This project is on schedule to be completed in May.
3.01.22 - Erectors continue to hang steel. The framing crews began framing the front facades. The paving crew will start pouring the paving soon,
12.02.22 - Crews began sheeting the buildings,
11.17.22 - Crews are erecting the first of the 12,000 SF flex office/warehouse spaces,
11.06.22 - Crewmen poured the first pad for this project. Spaces are available for sale or lease and range from 3,000 SF to 12,000 SF.
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/