12.22.20 - Crewmen are painting stripes and joint sealing in the NW paving area. Crewmen are also removing existing parking stripes.
12.18.20 - Crews are painting stripes and joint sealing in SE paving area only.
12.07.20 - Crews are dewatering the site, spreading spoils, and loading materials and cleaning equipment.
11.20.20 - The NE paving pour is underway,
11.14.20 - Storm work continues,
11.11.20 - Crewmen are laying storm,
11.10.20 -
11.05.20 - Crews began pouring the paving this morning,