8.14.20 - This project is complete,
8.06.20 - Final clean is scheduled for next week,
7.07.20 - Waiting on power,
6.12.20 - Irrigation installation is underway. The crane installation is complete. Once this project has final power, crews will complete the AC, flooring, MEP trim out, and interior office painting,
5.29.20 - The entrance canopy is installed,
5.28.20 - Stone is complete and the interior walls are two sided, taped, and floated. AC grills will be completed today,
4.21.20 - Walls and roof are sheeted. The overhead doors are being installed, and the office framing, AC work, and plumbing rough in has begun,
4.13.20 - The building is 60% complete. Crewmen started to frame the office. Paving and curbs are completed,
3.30.20 - Erectors continue to hang steel as additional crews prepare for next weeks pour,
3.25.20 - Erectors are unloading steel,
3.18.20 - The foundation was poured today,
3.13.20 - Plumbing and electrical groundout are waiting on inspections. Crews are digging grade beams and seting steel, preparing to pour next Wednesday,
3.11.20 - Crews are setting p the slab for next week's pour. Crews are also plumbing ground out for the fire line,
3.02.20 - Finishing up subgrade for paving. Steel has been delivered,
2.20.20 - Crews finished installing the storm and will continue to form the pad,
12.27.19 - Crews have begun sitework for Grizzly's new facility. Dennis Montesinos is the PM and Kenneth Whitmill is the Superintendent,
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/