Joe's Burgers and Subway Restaurants

Traders Village | 4,000 SF Freestanding Joe's Burgers Restaurant / 4,000 SF Freestanding Subway Restaurant | Houston, TX

10.10.19 - Subway will open next weekend. Below are final photos of this project. Final photos of Joe's Burgers are below Subway. Joe's Burgers will open this weekend,

IMG 8333

IMG 8283

IMG 8286

IMG 8302

IMG 8306

IMG 8307

IMG 8322

IMG 8375

IMG 8385

IMG 8296

IMG 8297

Joe's Burgers,

IMG 8344

IMG 6510

IMG 6528

IMG 6544

IMG 8350

IMG 8355

IMG 8359

IMG 8366

 

10.02.19 - A final clean is underway for Subway,

IMG 6580

IMG 6582

IMG 6584

IMG 6587

IMG 6593

IMG 6595

IMG 6596

IMG 6598

IMG 6600

IMG 6601

IMG 6605

 

10.01.19 - Joe's Burgers is complete,

IMG 3929

IMG 3931

IMG 3932

IMG 3933

IMG 3934

IMG 3936

 

 

9.24.19 - Joe's Burgers will be complete after the fire inspection and crewmen will wrap up their work on Subway at the end of the week,

IMG 3896

IMG 3893

IMG 3894

IMG 3895

IMG 3898

 

8.21.19 - Crews began installing the stainless steel countertops and pass through window at Joe's Burgers,

2

3

4

7

5

8

13

Subway - Crews continue to install the metal facade and the vent hood,

1

2

 

 

8.20.19 - Electricians are building the service at Joe's Burgers. The galvanized pipe ceiling treatment is being hung and the kitchen equipment has arrived and is getting installed,

joes8.20 2

joes8.20 3

joes8.20

Subway - Metal facade is being installed. Electricians are hanging the pendant fixtures in the dining area. Kitchen wall tile installation is also underway.

subway8.20 2

subway8.20 3

subway8.20 4

subway8.20

8.09.19 - Crews are applying epoxy flooring in the kitchen area of Joe's Burgers, while M&M crewmen install the framing for canopies and the roof for the wash bay. Finishers are taping and floating at Subway. FRP is being installed in the kitchen. Electricians are running conduit,

IMG 1431

IMG 1435

IMG 1437

IMG 1439

IMG 1446

IMG 1448

IMG 1450

IMG 1454

IMG 1457

IMG 1458

IMG 1466

 

7.29.19 - Paving and tile work are complete for Joe's Burgers,

1

2

3

4

6

 

7.08.19 - Masons continue to lay the brick as Carpenters install the ceiling treatments for Joe's Burgers. Roofers are installing curbs and electricians are roughing in the lights and switches at Subway.

Joes7.08 2

Joes7.08 3

Joes7.08 4

Joes7.08

Subway,

subway7.08 4

subway7.08 2

subway7.08 3

subway7.08

 

6.27.19 - Spiral ductwork is complete for Joe's Burgers. Vent-a-hood is installed. Masons started the brickwork. 

IMG 8011

IMG 8012

IMG 8014

IMG 8016

IMG 8018

IMG 8019

 

6.25.19 - Window frames are installed and the roof is complete for Joe's Burgers. Electricians are roughing in the electrical, while HVAC contractors hang the spiral ductwork. --The block and water proofing is complete for Subway. Curbs are set and roofers began installing the iso board,

IMG 3124

3

IMG 3129

IMG 3130

1

 

6.07.19 - Crewmen are installing hat channels for Joe's Burgers, and hanging steel for Subway,

IMG 3088

IMG 3089

IMG 3090

IMG 3091

IMG 3092

IMG 3093

6.03.19 - Crews have been addressing the CMU installation, setting embedded plates for the bar joists, and filling walls with concrete. As for Joe's Burgers, crewmen are laying out the roof curbs for the AC and vents, cutting AC access and welding angle supports, framing, and pouring interior curbs. Electrical rough-in is also underway. 

1

2

3

4

 

5.29.19 - Crewmen began CMU installation for the Subway restaurant, which will be completed by the end of this week. We expect steel for this building to be delivered on 5/31, and will begin erecting. 

Steel erecting is complete and inspected for Joe's Burgers. The roof deck is on and framing has begun. Crewmen plan to pour interior curbs and block outs this week, so framing and plywood can be completed.

4

1

2

1

2

3

4

5

6

 

5.06.19 - Erectors began hanging steel and the masons continue to build the CMU walls,

IMG 7756

IMG 7757

IMG 7760

IMG 7761

4.29.19 - . Joes slab was poured last week.  Cmu install is scheduled to start today. As for Subway, crewmen were able to pour beams and prep for the slab pour. Subway's slab pour is scheduled for today and tomorrow.

joes

joes3

joes4

joes5

subway

4.03.19 - Underground is complete. Crews are digging beams and tying steel in preparation for next week's concrete pour,

IMG 7603

IMG 7608

IMG 7609

IMG 7610

 

3.25.19 - Crews are pouring piers today for Joe's Burgers. Plumbers ran the utilities for Subway and are backfilling today,

IMG 7555

IMG 7557

IMG 7558

 

 

3.20.19 - The existing slabs are removed. Plumbers have made the utility connections and the boring for the fire main is complete. Concrete crews began tying steel for the piers.

IMG 7513

IMG 7514

IMG 7515

IMG 7516

3.17.19 - Crewmen ran utilities and poured trench for Joe's Burgers, and finished removing the slab for Subway,

1

2

3

4

5

3.08.19 - Crewmen are saw cutting and breaking out existing slabs, making tie-ins for water, sewer, and gas. 