6.02.22 - Power was turned on today. Flooring and the ceiling tile installation will follow,
3.03.22 - Interior framing is underway,
2.08.22 - Erectors began hanging the steel today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/