6.02.22 - Crewmen are addressing punch out items and the project will be completed by next week,
5.11.22 - This project is complete. Waiting on power,
3.18.22 - The stucco is complete. The ceiling grid installation is underway, and the electricians are installing the lights,
3.02.22 - Crews have made great progress this month. The paving is complete and masonry has begun. Interior crews continue to hang sheetrock,
2.15.22 - Interior crews are hanging drywall and the concrete crewmen are forming the paving. The excavation of the business park's eastern retention pond is almost complete,
1.19.22 - Erectors are sheeting the roof. Framers are framing the walls.
1.04.22 - Erectors are hanging steel for this new facility,
12.16.21 - Crews are preparing for the foundation pour,
11.11.21 - Site work is underway for a new 20,000 SF trade school, located at 20213 Binford Rd,
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/