7.06.22 - This project is complete,
6.02.22 - Masonry work is underway, in addition to electrical and the office build-out,
5.11.22 - Canopies are being installed. M&M is trimming out the wash bay building. The asphalt drive is complete,
3.18.22 - Erectors continue to sheet the building. The concrete crew is scheduled to pour the parking lot next week,
3.02.22 - Erectors continue to hang steel. The pre-assembles are complete and crews are filling in the intermediate bays,
2.15.22 - Erectors are hanging sections of roof,
1.19.22 - Crews are pouring the second half of the foundation,
11.11.21 - Site work is underway for Elite RV's new 70,000 SF conceirege service storage center for motorcoaches,
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/