Completed project photos,
6.08.20 - Painting is near completion. This project will be completed next week, following landscaping,
5.07.20 - Masonry contractors completed the stucco. The wall tile in the restrooms is being installed. M&M Erectors are trimming the building and installing the entry canopy,
4.30.20 - Painters completed their work painting the walls and ceilings. Door frames are being installed. The masonry contractor began the stucco facade,
4.23.20 - The entry canopy is complete. Painters are spraying the exposured structure. Electricians are building the service panels,
4.14.20 - AVAdek is installing the entry pergola. HVAC ductwork is being installed. Electricians are roughing in the plugs and switches,
4.02.20 - Interior buildout continues, window and door installation are also underway,
3.10.20 - Roof sheeting and siding are underway,
3.02.20 - Crewmen have finished sheeting the east wall,
2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,
2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,
2.15.20 - Crews are pouring the foundation,
2.11.20 - Crews are prepping for the foundation pour,
12.14.19 - Crewmen plan to pour paving on Monday,
12.12.19 - Site work continues,
Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,
3.10.20 - Roof sheeting and siding are underway,
3.02.20 - Crewmen have finished sheeting the east wall,
2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,
2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,
2.15.20 - Crews are pouring the foundation,
2.11.20 - Crews are prepping for the foundation pour,
12.14.19 - Crewmen plan to pour paving on Monday,
12.12.19 - Site work continues,
Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,
By accepting you will be accessing a service provided by a third-party external to https://northwindscommercialrealty.com/