twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

Northwinds Construction

View important updates by Northwinds Construction

Grizzly

Grizzly | 35,000 SF Office/Warehouse | Waller, TX

8.14.20 - This project is complete,

IMG 9062

IMG 9067

IMG 9072

IMG 9078

IMG 9086

IMG 9089

IMG 9093

IMG 9111

IMG 9113

IMG 9117

IMG 9118

IMG 9120

IMG 9133

IMG 9134

IMG 9139

IMG 9141

IMG 9142

IMG 9152

IMG 9147

 

8.06.20 - Final clean is scheduled for next week,

5

1

3

2

4

 

7.07.20 - Waiting on power,

thumbnail IMG 4435

thumbnail IMG 4436

thumbnail IMG 4437

thumbnail IMG 4438

thumbnail IMG 4439

thumbnail IMG 4440

thumbnail IMG 4441

thumbnail IMG 4442

 

6.12.20 - Irrigation installation is underway. The crane installation is complete. Once this project has final power, crews will complete the AC, flooring, MEP trim out, and interior office painting,

thumbnail IMG 4367

thumbnail IMG 4366

thumbnail IMG 4365

5.29.20 - The entrance canopy is installed,

20200529 172816542 iOS

5.28.20 - Stone is complete and the interior walls are two sided, taped, and floated. AC grills will be completed today,

20200528 212521859 iOS

20200528 212449662 iOS

20200528 212410365 iOS

20200528 211646779 iOS

20200528 211633528 iOS

20200528 210553694 iOS

20200528 204910696 iOS

20200528 204712186 iOS

20200528 204727450 iOS

20200528 204831021 iOS

20200528 204835542 iOS

20200528 204850432 iOS

 

4.21.20 - Walls and roof are sheeted. The overhead doors are being installed, and the office framing, AC work, and plumbing rough in has begun,

4.21 grizzly3

4.21 grizzly

4.21 grizzly2

4.21 grizzly4

4.21 grizzly5

4.21 grizzly6

4.13.20 - The building is 60% complete. Crewmen started to frame the office. Paving and curbs are completed,

20200413 140858720 iOS

20200413 140539370 iOS

 

3.30.20 - Erectors continue to hang steel as additional crews prepare for next weeks pour,

20200330 152427116 iOS

20200330 151907978 iOS

20200330 151910825 iOS

 

3.25.20 - Erectors are unloading steel,

20200325 132752869 iOS 1

 

3.18.20 - The foundation was poured today,

20200318 120911923 iOS

20200318 172750541 iOS

 

3.13.20 - Plumbing and electrical groundout are waiting on inspections. Crews are digging grade beams and seting steel, preparing to pour next Wednesday,

1

2

4

3.11.20 - Crews are setting p the slab for next week's pour. Crews are also plumbing ground out for the fire line,

IMG 3831

IMG 3835

IMG 3833

IMG 3834

3.02.20 - Finishing up subgrade for paving. Steel has been delivered,

IMG 3795

IMG 3797

IMG 3796

 

2.20.20 - Crews finished installing the storm and will continue to form the pad,

IMG 4415

IMG 4416

IMG 4417

 

12.27.19 - Crews have begun sitework for Grizzly's new facility. Dennis Montesinos is the PM and Kenneth Whitmill is the Superintendent,

Grizzly12.27.19 4

Grizzly12.27.19

Grizzly12.27.19 5

  4587 Hits
Tags:
4587 Hits