twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

Northwinds Construction

View important updates by Northwinds Construction

Connect Church

Connect Church | New 12,000 SF Facility | Montgomery, TX

1.26.22 - This was such a fun project. Below are final photos of their new church,

IMG 1768

IMG 1666

IMG 1787

IMG 1690

IMG 1704

IMG 1717

IMG 1720

IMG 1710

IMG 1728

IMG 1732

IMG 1714

IMG 1676

IMG 1803

IMG 1644

IMG 1650

IMG 1815

 

 

 

11.20.21 - This project is nearing completion. Floor installation is underway, as interior painting continues. Start-up crewmen are installing AC units. The final clean and completion are scheduled for next week,

IMG 0589

IMG 0532

IMG 0538

IMG 0545

IMG 0548

IMG 0556

IMG 0564

IMG 0569

IMG 0570

IMG 0572

IMG 0578

IMG 0579

IMG 0580

IMG 0583

IMG 0585

 

 

11.10.21 - Electricians are tieing in homeruns and pulling wire into the sanctuary, bathroom tile installation continues, and masons continue bricking the exterior. Erectors began trimming the building and plumbers set 5 septic tanks,

20211110 084810 photo 20211110 084800

20211108 071738 photo 20211108 071700

20211027 133438 photo 20211027 083400

20211027 133510 photo 20211027 083500

20211027 133525 photo 20211027 083500

20211028 131710 photo 20211028 081700

20211102 122947 photo 20211102 072900

20211104 140445 photo 20211104 090400

20211108 071524 photo 20211108 071500

20211109 071746 photo 20211109 071700

20211028 131810 photo 20211028 081800

20211110 084625 photo 20211110 084600

 

 

10.19.20 - The ceiling grid is installed and door frames are being installed,

ConnectChurch10.19 3

ConnectChurch10.19 10

ConnectChurch10.19 2

ConnectChurch10.19 4

ConnectChurch10.19 5

ConnectChurch10.19 6

ConnectChurch10.19 7

ConnectChurch10.19 8

ConnectChurch10.19 9

ConnectChurch10.19 11

ConnectChurch10.19 13

ConnectChurch10.19 14

ConnectChurch10.19 15

ConnectChurch10.19 16

ConnectChurch10.19

 

 

10.15.21 - The electricians are pulling wire as additional crews clean the site and reset the silt fence. The data wire is also being run.

20211015 121605 photo 20211015 071500

20211015 121632 photo 20211015 071600

20211015 121653 photo 20211015 071600

20211015 121713 photo 20211015 071700

20211015 122326 photo 20211015 072300

20211015 122340 photo 20211015 072300

20211015 122355 photo 20211015 072300

20211015 122424 photo 20211015 072400

 

9.12.21 - The glass is installed. Drywall, electrical, and HVAC work continue,

IMG 5736

IMG 5739

IMG 5748

IMG 5698

IMG 5751

IMG 5754

IMG 5709

IMG 5710

IMG 5711

IMG 5713

IMG 5714

IMG 5717

 

9.02.21 - Framers are hanging drywall. HVAC crewmen are hanging the ductwork,

IMG 2374

IMG 2375

IMG 2377

IMG 2384

IMG 2385

IMG 2386

IMG 2390

 

8.24.21 - The exterior walls are up and interior framing and buildout are underway,

 1946238176 20210824 151228 3137053 resized

1515713178 20210824 151145 3306461 resized

 89960966 20210824 151453 2315671 resized

 146295747 20210824 151434 2853758 resized

 918953949 20210824 151825 2866278 resized

 1118763360 20210824 151305 3651506 resized

 

8.04.21 - Erectors have progressed to hanging the pre-assembled roof sections,

8.04.21 10

8.04.21 7

8.04.21

 

8.02.21 - Erectors are into their second day hanging steel,

IMG 3565

IMG 3578

IMG 3593

IMG 3591

 

7.23.21 - The foundation is cured and saw cut. Steel delivery is scheduled for tomorrow,

ConnectChurch7.27 2

ConnectChurch7.27 3

ConnectChurch7.27 4

ConnectChurch7.27 5

ConnectChurch7.27

 

7.22.21 - Crews began pouring the foundation for the church building this morning,

ConnectChurchPour5

ConnectChurchPour11

 

7.01.21 - Crews laid out form boards, and finished digging grade beams. Electricians are working on underground electrical for the foundation.

ConnectChurch7.01

ConnectChurch7.01 2

6.30.21 - Electricians are laying out the underground electrical,

20210630 152021 photo 20210630 102000

20210630 152054 photo 20210630 102000

20210630 152103 photo 20210630 102100

20210630 152234 photo 20210630 102200

 

6.26.21 - The plumbers continue underground plumbing,

20210626 125234 photo 20210626 075200

20210626 125248 photo 20210626 075200

20210626 125350 photo 20210626 075300

6.24.21 - Underground plumbing continues,

20210624 153523 photo 20210624 103500

20210625 152216 photo 20210625 102200

20210625 152246 photo 20210625 102200

 

6.22.21 - Crewmen cleared shrubs along the drive for the future sign. Additional crews spread lime to speed the drying time of the job site, and laid out grade beam locations,

20210622 141801 photo 20210622 091700

20210623 145709 photo 20210623 095700

 

6.18.21 - Crewmen drilled and poured piers. Electricians installed conduit for light poles.

20210618 151251 photo 20210618 101200 copy

20210618 151205 photo 20210618 101200

 

5.14.21 - Curbs were poured for the parking area and have cured,

ConnectChurch curbs

ConnectChurch curbs2

ConnectChurch curbs3

ConnectChurch curbs4

 

4.27.21 - Crewmen are pouring the parking areas today,

CChurchPavingPour4.27.21 6

CChurchPavingPour4.27.21 24

 

3.16.21 - Crewmen continue their work on the pond outfall, digging out the second box, with stabilization, rest box and pipe, backfill, and dress up,

20210315 134322 photo 20210315 134300

20210315 091243 photo 20210315 091200

20210315 130913 photo 20210315 130900

20210315 130922 photo 20210315 130900

 

1.12.21 - Site crewmen continue excavating the detention pond and grading the site,

8

6

4

12.23.20 - Crews are clearing the site to prepare for the church's building pad,

ConnectChurch12.23 2

ConnectChurch12.23 3

ConnectChurch12.23 4

 

Sitework will soon begin for Connect Church's new 12,000 SF facility. The new church facility will include a sactuary, class rooms, and administrative offices,

02.1 Elevation

03.1 Interior sanctuary

  4897 Hits
4897 Hits