twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

26106 Clay Road

26106 Clay Road | 12,000 SF PEMB | Katy, TX

12.15.19 - This property Available for Sale or Lease. Call for more information, 713-671-5300.

IMG 8656

IMG 8647

IMG 8648

IMG 8660

IMG 8665

IMG 8667

IMG 8668

IMG 8670

IMG 8673

IMG 8676

IMG 8677

IMG 8680

IMG 8682

IMG 8684

IMG 8687

IMG 8692

IMG 8698

IMG 8702

 

12.03.19 - Below are photos of the final interior,

IMG 3495

IMG 3496

IMG 3498

IMG 3499

IMG 3500

IMG 3501

IMG 3502

 

10.05.19 - Landscaping is complete and flooring is near completion,

IMG 7223

IMG 7221

IMG 7217

IMG 7174

IMG 7175

IMG 7178

IMG 7182

IMG 7183

IMG 7186

IMG 7187

IMG 7190

IMG 7191

IMG 7194

IMG 7195

IMG 7203

IMG 7208

IMG 7211

9.27.19 - Power has been set on the building. Landscaping is being installed. Next week the ceiling tiles and flooring will be installed,

IMG 8702

IMG 8708

IMG 8714

IMG 8716

IMG 8717

IMG 8719

IMG 8720

 

9.13.19 - Flooring and landscape installation are underway,

IMG 5704

IMG 5705

 

8.09.19 - Electricians continue to run lights in the warehouse, while plumbers work on the waterline. Painting is underway. M&M Erectors finished trimming out the building,

9

5

1

2

3

4

8

15

7.11.19 - Masons are laying the stone. Interior crews are framing the walls. Septic tanks are being installed,

IMG 8120

IMG 8132

IMG 8133

IMG 8135

IMG 8138

IMG 8139

IMG 8140

IMG 8141

 

6.28.19 - This office/warehouse is now fully sheeted. Interior framing is underway, as additional crewmen frame for the next paving pours, and the erectors trim the facility,

IMG 7768

IMG 7792

IMG 7795

IMG 7800

IMG 7834

 

6.06.19 - Erectors have progressed to installing the wall and skylight sheeting,

IMG 3084

IMG 3081

IMG 3083

IMG 3082

IMG 3085

 

3.25.19 - Crews poured the front paving last week,

20190321 141657

IMG 48

IMG 53

3.20.19 - Driveway is poured and the pad is complete. Concrete crews will be pouring the front half of the paving tomorrow,

26101_Clay_Rd

IMG 7530

IMG 7531

IMG 7532

IMG 7536

IMG 7537

  5387 Hits
5387 Hits

SiteOne - Friendswood

SiteOne | 7,000 SF PEMB | Friendswood, TX

12.09.19 - This project was completed in November and SiteOne is moving in,

IMG 9301

IMG 9303

 

10.14.19 - Interior painting is underway and landscaping installation will soon follow,

72457110 2969492139732264 2430015757896122368 n

72299795 2969492173065594 6244526975415746560 n

72326290 2969492286398916 1386470173917052928 n

72391726 2969492233065588 7505377237189787648 n

72752925 2969492336398911 318041958901612544 n

72964882 2969492279732250 3045147798732275712 n

73323856 2969492346398910 909502897371217920 n

73364215 2969492226398922 4111151405924876288 n

 

9.27.19 - Painters are wrapping up. Site crew is cleaning up the site. The building should have power next week,

IMG 8681

IMG 8683

IMG 8684

IMG 8685

IMG 8691

IMG 8692

IMG 8694

IMG 8695

IMG 8696

IMG 8698

 

9.09.19 - Crews are tying steel in preparation for Wednesday's paving pour,

IMG 8560

IMG 8561

IMG 8562

IMG 8564

IMG 8565

IMG 8567

IMG 8568

IMG 8569

IMG 8570

IMG 8571

IMG 8572

 

8.19.19 - The building is fully sheeted and trimmed. Downspouts are installed and the side canopy. Interior framing is underway,

IMG 6099

IMG 6097

IMG 6095

8.09.19 - M&M Erectors continue to sheet the roof. Site crewmen are grading for paving,

8 5 8 9 Field Report Export 002

2

5

3

4

6

 

7.23.19 - Crewmen are erecting the building,

siteone thumb

7.10.19 - Crews are tying steel for tomorrow morning's pour,

IMG 8102

IMG 8100

IMG 8108

 

6.28.19 - Sitework continues,

IMG 2447

IMG 2446

 

6.26.19 - Crews broke ground on this project last week. It will be a new 7,000 SF retail center and showroom for a wholesale landscape and irrigation supplier SiteOne. Trevor Robinson is the PM.

SOF1 thumb

SOF2 thumb

IMG 1706

IMG 2441

  5759 Hits
5759 Hits

Wilson Air

Wilson Air | 28,000 SF Additional Airplane Hangar and Office | Houston, TX

10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,

IMG 9243

IMG 9242

IMG 9240

IMG 9236

IMG 9223

IMG 9222

IMG 9220

IMG 9218

IMG 9206

IMG 9186

IMG 9147

IMG 9074

IMG 9028

IMG 9029

IMG 9036

IMG 9037

IMG 9038

IMG 9130

IMG 9138

IMG 9046

IMG 9050

IMG 9069

IMG 9073

IMG 9102

IMG 9108

IMG 9105

IMG 9117

IMG 9099

IMG 9119

IMG 9126

IMG 9085

 

9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,

IMG 8504

IMG 8505

IMG 8506

IMG 8508

IMG 8509

IMG 8510

IMG 8511

 

9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,

1

2

5

10

13

14

15

16

20

31

32

 

8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,

3

1

4

2

 

6.03.19 - Electricians are running extra grounding and cad welding to the columns,

9

4

5

8

 

4.29.19 -  Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,

1

3

4

10

14

16

17

22

 

4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,

IMG 3916

IMG 3870

IMG 3880

IMG 3899

4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,

IMG 7585

IMG 7588

IMG 7590

IMG 7592

IMG 7593

IMG 7596

3.29.19 - Liner panels are being installed,

IMG 1035

IMG 1036

IMG 1037IMG 1038IMG 1040

3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,

19

23

27

3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,

IMG 0870

IMG 0871

IMG 0872

IMG 0873

IMG 0874

IMG 0875

 

2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,

IMG 2718

IMG 2719

IMG 2720

IMG 2721

 

1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,

IMG 0354

IMG 0355

IMG 0356

IMG 0357

1.07.19 - Hanging rafters,

IMG 2601

IMG 2603

 

12.18.18 - Crews began hanging steel last week,

IMG 0055

IMG 0056

IMG 0057

 

 

12.03.18 - The foundation has been saw cut,

IMG 3400

11.29.18 - The foundation was poured this week,

 IMG 0197

IMG 0205

IMG 0717

 

11.19.18 - Crewmen are tying double rebar mat for the foundation,

3

4

5

 

10.21.18 - Crewmen  have drilled 27 of the 32 piers,

13

1

10

14

9.24.18 - Crews are building pad for the foundation,

3

5

6

 

9.07.18 - Site excavation continues,

4

1

2

3

 

8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,

IMG 6308

A

B

6

 

  5871 Hits
5871 Hits

Joe's Burgers and Subway Restaurants

Traders Village | 4,000 SF Freestanding Joe's Burgers Restaurant / 4,000 SF Freestanding Subway Restaurant | Houston, TX

10.10.19 - Subway will open next weekend. Below are final photos of this project. Final photos of Joe's Burgers are below Subway. Joe's Burgers will open this weekend,

IMG 8333

IMG 8283

IMG 8286

IMG 8302

IMG 8306

IMG 8307

IMG 8322

IMG 8375

IMG 8385

IMG 8296

IMG 8297

Joe's Burgers,

IMG 8344

IMG 6510

IMG 6528

IMG 6544

IMG 8350

IMG 8355

IMG 8359

IMG 8366

 

10.02.19 - A final clean is underway for Subway,

IMG 6580

IMG 6582

IMG 6584

IMG 6587

IMG 6593

IMG 6595

IMG 6596

IMG 6598

IMG 6600

IMG 6601

IMG 6605

 

10.01.19 - Joe's Burgers is complete,

IMG 3929

IMG 3931

IMG 3932

IMG 3933

IMG 3934

IMG 3936

 

 

9.24.19 - Joe's Burgers will be complete after the fire inspection and crewmen will wrap up their work on Subway at the end of the week,

IMG 3896

IMG 3893

IMG 3894

IMG 3895

IMG 3898

 

8.21.19 - Crews began installing the stainless steel countertops and pass through window at Joe's Burgers,

2

3

4

7

5

8

13

Subway - Crews continue to install the metal facade and the vent hood,

1

2

 

 

8.20.19 - Electricians are building the service at Joe's Burgers. The galvanized pipe ceiling treatment is being hung and the kitchen equipment has arrived and is getting installed,

joes8.20 2

joes8.20 3

joes8.20

Subway - Metal facade is being installed. Electricians are hanging the pendant fixtures in the dining area. Kitchen wall tile installation is also underway.

subway8.20 2

subway8.20 3

subway8.20 4

subway8.20

8.09.19 - Crews are applying epoxy flooring in the kitchen area of Joe's Burgers, while M&M crewmen install the framing for canopies and the roof for the wash bay. Finishers are taping and floating at Subway. FRP is being installed in the kitchen. Electricians are running conduit,

IMG 1431

IMG 1435

IMG 1437

IMG 1439

IMG 1446

IMG 1448

IMG 1450

IMG 1454

IMG 1457

IMG 1458

IMG 1466

 

7.29.19 - Paving and tile work are complete for Joe's Burgers,

1

2

3

4

6

 

7.08.19 - Masons continue to lay the brick as Carpenters install the ceiling treatments for Joe's Burgers. Roofers are installing curbs and electricians are roughing in the lights and switches at Subway.

Joes7.08 2

Joes7.08 3

Joes7.08 4

Joes7.08

Subway,

subway7.08 4

subway7.08 2

subway7.08 3

subway7.08

 

6.27.19 - Spiral ductwork is complete for Joe's Burgers. Vent-a-hood is installed. Masons started the brickwork. 

IMG 8011

IMG 8012

IMG 8014

IMG 8016

IMG 8018

IMG 8019

 

6.25.19 - Window frames are installed and the roof is complete for Joe's Burgers. Electricians are roughing in the electrical, while HVAC contractors hang the spiral ductwork. --The block and water proofing is complete for Subway. Curbs are set and roofers began installing the iso board,

IMG 3124

3

IMG 3129

IMG 3130

1

 

6.07.19 - Crewmen are installing hat channels for Joe's Burgers, and hanging steel for Subway,

IMG 3088

IMG 3089

IMG 3090

IMG 3091

IMG 3092

IMG 3093

6.03.19 - Crews have been addressing the CMU installation, setting embedded plates for the bar joists, and filling walls with concrete. As for Joe's Burgers, crewmen are laying out the roof curbs for the AC and vents, cutting AC access and welding angle supports, framing, and pouring interior curbs. Electrical rough-in is also underway. 

1

2

3

4

 

5.29.19 - Crewmen began CMU installation for the Subway restaurant, which will be completed by the end of this week. We expect steel for this building to be delivered on 5/31, and will begin erecting. 

Steel erecting is complete and inspected for Joe's Burgers. The roof deck is on and framing has begun. Crewmen plan to pour interior curbs and block outs this week, so framing and plywood can be completed.

4

1

2

1

2

3

4

5

6

 

5.06.19 - Erectors began hanging steel and the masons continue to build the CMU walls,

IMG 7756

IMG 7757

IMG 7760

IMG 7761

4.29.19 - . Joes slab was poured last week.  Cmu install is scheduled to start today. As for Subway, crewmen were able to pour beams and prep for the slab pour. Subway's slab pour is scheduled for today and tomorrow.

joes

joes3

joes4

joes5

subway

4.03.19 - Underground is complete. Crews are digging beams and tying steel in preparation for next week's concrete pour,

IMG 7603

IMG 7608

IMG 7609

IMG 7610

 

3.25.19 - Crews are pouring piers today for Joe's Burgers. Plumbers ran the utilities for Subway and are backfilling today,

IMG 7555

IMG 7557

IMG 7558

 

 

3.20.19 - The existing slabs are removed. Plumbers have made the utility connections and the boring for the fire main is complete. Concrete crews began tying steel for the piers.

IMG 7513

IMG 7514

IMG 7515

IMG 7516

3.17.19 - Crewmen ran utilities and poured trench for Joe's Burgers, and finished removing the slab for Subway,

1

2

3

4

5

3.08.19 - Crewmen are saw cutting and breaking out existing slabs, making tie-ins for water, sewer, and gas. 

IMG 2904 thumb

IMG 2905

 

 

 

 

 

 

 

  6816 Hits
6816 Hits

Word of God Christian Fellowship Church

Word of God Christian Fellowship Church | 12,000 SF Facility | Cypress, TX

Parking lot expansion is complete,

IMG 2435

IMG 2436

IMG 2437

12.21.18 - Fire inspection is underway,

IMG 5574

IMG 5579

IMG 5899

IMG 5900

IMG 5901

IMG 5903

IMG 5907

IMG 5910

IMG 5911

IMG 5928

IMG 5932

IMG 5936

IMG 55742

12.20.18 - Final clean is complete. MUD District inspection is tomorrow, and the final fire inspection is Friday,

IMG 2023

IMG 2024

IMG 2025

IMG 2026

IMG 2028

IMG 2029

IMG 2031

IMG 2035

12.14.18 - This project is nearing completion. A final clean is scheduled for next week,

IMG 5426

IMG 5790

IMG 5792

IMG 5803

IMG 5804

IMG 5807

IMG 5810

IMG 5811

IMG 5815

IMG 5831

IMG 5835

IMG 5846

IMG 5851

IMG 5852

IMG 5862

IMG 5863

IMG 5877

IMG 5879

 

 11.01.18 - Lights on and painters are applying final coat of paint,

Dq7lJLpU4AAKskJ

10.30.18 - Lighting is complete. Crewmen are finishing the second coat of paint in the sanctuary,

IMG 3856

IMG 3854

IMG 3855

9.12.18 - Crewmen are sheetrocking walls while Electricians rough in lighting,

IMG 2671

IMG 2668

IMG 2679

IMG 2673

IMG 2674

IMG 2675

IMG 2676

IMG 2677

IMG 2681

IMG 2672

 

8.13.18 - Electricians are roughing in the electrical, Mechanical contractors are installing ductwork, Finishers are taping and floating sheetrock, and M&M crewmen are installing the soffit and trim,

IMG 1949

IMG 1950

IMG 1951

IMG 1952

IMG 1953

IMG 1954

IMG 1955

IMG 1956

IMG 1957

IMG 1958

IMG 1959

 

7.20.18 - Masonry and roof sheeting are underway. Crewmen are also framing the interior walls. Flatwork is 80% complete,

IMG 1925

IMG 1928

IMG 1929

IMG 1930

IMG 1931

IMG 1932

IMG 1933

IMG 1937

 

7.11.18 - Wall sheeting continues,

IMG 1805

IMG 1806

IMG 1807

 

7.03.18 - Crewmen are forming up for aditional paving and installing additional purlins. Sheeting continues,

IMG 1730

IMG 1731

IMG 1728

IMG 1729

 

 

6.28.18 - Crewmen are pouring the first phase of paving this morning,

FullSizeRender

FullSizeRender2

6.25.18 - Crewmen are forming up paving. Wall sheeting has begun,

IMG 1634

IMG 2186

6.18.18 - Progress erecting the church building,

WordofGod6.18.18

WordofGod6.18.18 2

6.13.18 - The building and detention lift station arrived,

WordofGodChristianFellowshipChurch6.13.18 2

WordofGodChristianFellowshipChurch6.13.18

6.11.18 - Flat work will begin in next few days,

WordofGod6.11.18

WordofGod6.11.18 2

5.30.18 - The foundation pour is underway this morning,

IMG 2075

5.23.18 - Storm pipe installation, foundation ground out and forms,

IMG 2066

IMG 2065

5.11.18 - Crewmen are drilling and pouring foundation piers today,

1

2

4.25.18 - The big pond is 75% complete and the pad is 3" above final grade. Waiting on final compaction test today. 

1

3

 

4.02.18 - Crews began excavating the detention ponds and continue to dewater the site,

WordofGod4.03.18

WordofGod4.03.18 2

3.23.18 - The site has been stripped of parking area,

Word of God Church 3.21.18 3

Word of God Church 3.21.18 2

WOG3.23.18 2

WOG3.23.18 3

WOG3.23.18 4

Word of God Church 3.21.18

WOG3.23.18

5.20.17 - Today we celebrated at a ground-breaking ceremony for the Word of God Church. Construction will soon begin for their new place of worship.

WOG5.20.17 4

WOG5.20.17

WOG5.20.17 2

WOG5.20.17 3

  7515 Hits
7515 Hits

26110 Clay Road

26110 Clay Road | 12,000 SF PEMB | Katy, TX

This facility was purchased by Stillo Construction

11.01.18 - The building is complete. Parking lot cleaning and striping to follow,

IMG 6729

IMG 6732

IMG 6733

IMG 6741

IMG 6742

IMG 6743

IMG 6745

IMG 6746

IMG 6748

IMG 6749

IMG 6751

IMG 6754

 

9.12.18 - Masons are installing the cast stone. Grid for the acoustical ceiling is being installed,

IMG 2695

IMG 2697

IMG 2698

IMG 2700

IMG 2701

IMG 2702

IMG 2704

 

8.30.18 - Masonry work is underway as crewmen address HVAC and interior framing,

IMG 2167

IMG 2168

IMG 2169

IMG 2170

IMG 2171

IMG 2172

IMG 2174

IMG 2175

IMG 2176

 

7.20.18 - Crewmen are installing exterior sheathing and are framing interior walls,

IMG 1916

IMG 1914

IMG 1915

IMG 1917

IMG 1919

IMG 1920

IMG 1922

7.16.18 - Crewmen have progressed to roof sheeting,

IMG 1838

IMG 1839

IMG 1840

 

7.06.18 - Crewmen continue to sheet the walls,

IMG 1056

IMG 1057

IMG 1060

 

7.03.18 - All steel is hung and crewmen have progressed to sheeting the building,

IMG 1719

IMG 1722

IMG 1723

 

6.25.18 - Crewmen began hanging steel,

IMG 1663

IMG 1664

IMG 1665

IMG 1666

IMG 1667

 

5.01.18 - Paving is poured and sawcut. Crewmen begin seeding the detention pond,

IMG 1257

IMG 1258

IMG 1259

IMG 1260

IMG 1261

IMG 1262

IMG 1263

4.26.18 - Crewmen poured the paving this morning,

IMG 1964

 

4.12.18 - Crewmen are setting the storm for Spec Bldg 1. Electricians are trimming out electrical service panel for pond lift station and water well,

IMG 1929 thumb

IMG 1930

IMG 1931

3.28.18 - Crewmen poured the foundation this morning,

IMG 1803

3.23.18 - Excavation of the detention pond is complete. Slab is made up and ready to pour,

KatySpecBldg1 3.23.18

KatySpecBldg1 3.23.18 4

KatySpecBldg1 3.23.18 2

KatySpecBldg1 3.23.18 3

KatySpecBldg1 3.23.18 5

KatySpecBldg1 3.23.18 6

KatySpecBldg1 3.23.18 7

KatySpecBldg1 3.23.18 8

KatySpecBldg1 3.23.18 9

3.13.18 - Progress on the water tank and the detention pond,

Siteone3.13.18

Siteone3.13.18 2

Siteone3.13.18 3

1.09.18 - The pad is built for this new facility and crewmen are grading the detention pond. This new office/warehouse is Available for Sale or Lease, off Clay Rd in Katy,

KH1 exterior

KH1 exterior2

SpecBldg1

SpecBldg1 3

SpecBldg1 4

SpecBldg1 5

SpecBldg1 6

SpecBldg1 7

SpecBldg1 8

 

  6311 Hits
6311 Hits

16110 Clay Rd

16110 Clay Rd | 12,374 SF PEMB | Katy, TX

This project is complete,

final thumb

5.04.18 - Waiting on fire marshall approval and final clean.

IMG 1290

IMG 1298

IMG 1299

IMG 1300

IMG 1301

IMG 1302

IMG 1304

IMG 1308

IMG 1310

IMG 1313

IMG 1315

IMG 1316

IMG 1317

IMG 1320

IMG 1321

IMG 1323

 

4.02.18 - Waiting on fire marshal approval.

IMG 1260

3.23.18 -  Landscaping is underway. The building is complete. Addressing punch out items, cleaning up site, and waiting for power,

siteone3.23.18 10

siteone3.23.18 9

siteone3.23.18 6

siteone3.23.18 7

siteone3.23.18 6

siteone3.23.18 5

siteone3.23.18 4

siteone3.23.18 3

siteone3.23.18 2

siteone3.23.18

1.25.18 - Pouring retaining walls,

siteone1.25.18

siteone1.25.18 4

siteone1.25.18 3

siteone1.25.18 2

1.08.18 - Crewmen are currently taping and floating,

siteone1.08.18 10

siteone1.08.18 9

siteone1.08.18 8

siteone1.08.18 7

siteone1.08.18 6

siteone1.08.18 5

siteone1.08.18 4

siteone1.08.18 3

siteone1.08.18 2

12.13.17 - Crews poured paving this morning,

IMG 1358

IMG 1359

10.30.17 - Building is sheeted and interior framing underway,

IMG 7706

IMG 7707

10.25.17 - Sheeting continues,

IMG 7697

10.15.17 - Crewmen are hanging steel,

IMG 1064

10.06.17 - Pouring the foundation,

IMG 1046

9.15.17 - Pad progress,

siteone9.15.17

7.31.17 - Working on the pond and site grading,

SiteOne_7.31.17

6.28.17 - Site work began mid-June.

katybusinesspark6.28.17

5.31.17 - Sitework will soon begin for the first of 10 buildings in a new business park off Clay Road in Katy. This first building will be 12,374 SF (Total) with a 2,708 SF office and 9,666 SF Warehouse.

KH1 exterior

KH1 exterior2

 

  6551 Hits
6551 Hits